Centeris is planning a new data center in the Seattle market. The generators at the facility are designed to be N+1 redundant. The facility is designed to provide on-site connections to Zayo, Level 3 (Lumen Technologies) and Comcast upon construction.

Contact Centeris

Current status and power pipeline

Commissioned

This facility has been commissioned.

Planned

There are plans to add additional leaseable power.

Proximity to key digital infrastructure

location icon
location icon
1 mi

Location details

  • Building
  • Connectivity
  • Infrastructure
  • Compliance
  • Services
  • Security
Building
Year Built
1998
Purpose Built or Retrofit
Purpose Built
Building Size
200,000 SF
Building Owner
Centeris
Power
On Site Substation
Yes
Single or Dual Feed
Dual Feed
Market Avg Power Cost
4.49
Power Provider
dashed